The Generic Design Assessment (GDA) for the UK HPR1000 reactor technology was successfully completed by General Nuclear System Limited, with the issue of a Design Acceptance Confirmation (DAC) from the Office for Nuclear Regulation (ONR) and a Statement of Design Acceptability (SoDA) from the Environment Agency on 7 February 2022.
On this date we published the following documents:
- Pre-Construction Safety Report (PCSR) V2
- Pre-Construction Environmental Report (PCER) V2
- Generic Security Report V2
Some documents may contain commercially sensitive, export-controlled or sensitive nuclear information and so, in line with GDA guidance, we have made judgements on areas to be redacted prior to being made public.
You can view the joint announcement from the ONR and EA on their website. The Environment Agency’s report, including the Statement of Design Acceptability (SoDA) is available here. The Office for Nuclear Regulation reports can be viewed here.